LANDER 2018 STREETS REHABILITATION

71 Construction will be working in the areas of South 7th Street, Garfield Street, North 8th Street, Wood Street, and Madison Street through May 10, 2019.

If your property has orange paint marks, please park at least 20 feet away from those marked areas to allow room for concrete removal and replacement.

 

71 Construction will be working in the areas of Smith Street, Academic Way, Spriggs Drive, South Eighth Street, South Seventh Street, and Garfield Street through May 4, 2019.

If your property has orange paint marks, please park at least 20 feet away from those marked areas to allow room for concrete removal and replacement.

 

WEEKLY UPDATE FOR APRIL 15

71 Construction will be pouring concrete on the west end of Black Street just off of Smith Street from Monday through Thursday, April 15-18th. They will also be removing existing concrete on Spriggs Drive and preparing forms to pour new concrete on Friday on Spriggs Drive from April 15th to April 18th.

 71 Construction has scheduled to begin removing concrete and preparing forms to pour concrete on South 7th Street on Friday, April 19th.

 On Garfield Street, 71 Construction will be lowering manholes on Monday and Tuesday, April 15-16th.

 On North 8th Street, 71 Construction will be lowering manholes on Wednesday and Thursday, April 17th and 18th.

 On Wood Street, 71 Construction will be lowering manholes on Friday, April 19th.

 All plans are dependent upon weather conditions that allow site work.

 

 

 

Project Documents

You will need to login before you can see this project's documents.

Plan Holders of Record

You will need to login before you can see this project's plan holders.