CLIENT: Cedar Canyons, Inc. DATE: 2018-2021 SERVICES PROVIDED: Cost Estimating Regulatory Agency Coordination Contractor Negotiations NEPA Approval Road & River Crossing Design Cedar Canyons, Inc., was interested in first, obtaining a private inholding in the Shoshone National Forest. To determine if the property was feasible for the intended use, James […]
SERVICES PROVIDED: Cost Estimates for Bonding Preliminary Design DEQ Permitting To bring their world-altering energy source manufacturing facility to Wyoming, Inductance Energy asked James Gores and Associates to provide civil engineering services related to wastewater treatment for their facility in northwest Wyoming. The existing facility had a wastewater lagoon that had […]
71 Construction will not be working through the Independence Day holiday. Work will stop on July 3rd and resume on July 8th. On Smith Street, paving will occur on Tuesday, July 2nd and Wednesday, July 3rd. North 6th Street, 71 Construction will patch asphalt on July 1st. Kristen Court, 71 Construction will […]
January 18, 2018 – 9:35 am
CLIENT: The Curators of the University of Missouri DATE: 2017 SERVICES PROVIDED: Alternatives Study for Camp Operation Total Engineering Budget: $49,126.00 Preliminary & Final Engineering Design Construction Cost: $81,000.00 Construction Contract Documents Construction Observation As a […]
September 11, 2017 – 11:49 am
Removal of and replacement of site concrete flatwork, installation of trench drains for roof
downspout drainage, reconstructing brickwork on the building and retaining wall, construction
of ADA ramps, reconstruction of curb and gutter, and asphalt pavement replacement.